29 CFR 1926.1405: Disassembly—additional requirements for dismantling of booms and jibs (applies to both the use of manufacturer procedures and employer procedures).
Where this section sits in the code
- Title 29—Labor
- Subtitle B—Regulations Relating to Labor
- CHAPTER XVII—OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION, DEPARTMENT OF LABOR
- PART 1926—SAFETY AND HEALTH REGULATIONS FOR CONSTRUCTION
- Subpart CC—Cranes and Derricks in Construction
Dismantling (including dismantling for changing the length of) booms and jibs.
(a) None of the pins in the pendants are to be removed (partly or completely) when the pendants are in tension.
(b) None of the pins (top or bottom) on boom sections located between the pendant attachment points and the crane/derrick body are to be removed (partly or completely) when the pendants are in tension.
(c) None of the pins (top or bottom) on boom sections located between the uppermost boom section and the crane/derrick body are to be removed (partly or completely) when the boom is being supported by the uppermost boom section resting on the ground (or other support).
(d) None of the top pins on boom sections located on the cantilevered portion of the boom being removed (the portion being removed ahead of the pendant attachment points) are to be removed (partly or completely) until the cantilevered section to be removed is fully supported.