30 CFR 250.1723: What must I do when it is no longer necessary to maintain a well in temporary abandoned status?
Where this section sits in the code
- Title 30—Mineral Resources
- CHAPTER II—BUREAU OF SAFETY AND ENVIRONMENTAL ENFORCEMENT, DEPARTMENT OF THE INTERIOR
- SUBCHAPTER B—OFFSHORE
- PART 250—OIL AND GAS AND SULPHUR OPERATIONS IN THE OUTER CONTINENTAL SHELF
- Subpart Q—Decommissioning Activities
If you or BSEE determines that continued maintenance of a well in a temporary abandoned status is not necessary for the proper development or production of a lease, you must:
(a) Promptly and permanently plug the well according to § 250.1715;
(b) Remove any casing stub or mud line suspension equipment and any subsea protective covering. You must submit a request for approval to perform such work to the appropriate District Manager using form BSEE-0124, Application for Permit to Modify; and
(c) Clear the well site according to §§ 250.1740 through 250.1742.
Collected 2026-08-27T02:25:24Z. Source file · JSON