30 CFR 250.1726: When must I submit an initial platform removal application and what must it include?
Where this section sits in the code
- Title 30—Mineral Resources
- CHAPTER II—BUREAU OF SAFETY AND ENVIRONMENTAL ENFORCEMENT, DEPARTMENT OF THE INTERIOR
- SUBCHAPTER B—OFFSHORE
- PART 250—OIL AND GAS AND SULPHUR OPERATIONS IN THE OUTER CONTINENTAL SHELF
- Subpart Q—Decommissioning Activities
An initial platform removal application is required only for leases and pipeline rights-of-way in the Pacific OCS Region or the Alaska OCS Region. It must include the following information:
(a) Platform or other facility removal procedures, including the types of vessels and equipment you will use;
(b) Facilities (including pipelines) you plan to remove or leave in place;
(c) Platform or other facility transportation and disposal plans;
(d) Plans to protect marine life and the environment during decommissioning operations, including a brief assessment of the environmental impacts of the operations, and procedures and mitigation measures that you will take to minimize the impacts; and
(e) A projected decommissioning schedule.