30 CFR 250.714: Do I have to develop a dropped objects plan?
Where this section sits in the code
- Title 30—Mineral Resources
- CHAPTER II—BUREAU OF SAFETY AND ENVIRONMENTAL ENFORCEMENT, DEPARTMENT OF THE INTERIOR
- SUBCHAPTER B—OFFSHORE
- PART 250—OIL AND GAS AND SULPHUR OPERATIONS IN THE OUTER CONTINENTAL SHELF
- Subpart G—Well Operations and Equipment
If you use a floating rig unit in an area with subsea infrastructure, you must develop a dropped objects plan and make it available to BSEE upon request. This plan must be updated as the infrastructure on the seafloor changes. Your plan must include:
(a) A description and plot of the path the rig will take while running and pulling the riser;
(b) A plat showing the location of any subsea wells, production equipment, pipelines, and any other identified debris;
(c) Modeling of a dropped object's path with consideration given to metocean conditions for various material forms, such as a tubular (e.g., riser or casing) and box (e.g., BOP or tree);
(d) Communications, procedures, and delegated authorities established with the production host facility to shut-in any active subsea wells, equipment, or pipelines in the event of a dropped object; and
(e) Any additional information required by the District Manager as appropriate to clarify, update, or evaluate your dropped objects plan.
Collected 2026-08-27T02:25:24Z. Source file · JSON