30 CFR 27.9: Date for conducting tests.

Read at publisher ↗
Where this section sits in the code
  1. Title 30—Mineral Resources
  2. CHAPTER I—MINE SAFETY AND HEALTH ADMINISTRATION, DEPARTMENT OF LABOR
  3. SUBCHAPTER B—TESTING, EVALUATION, AND APPROVAL OF MINING PRODUCTS
  4. PART 27—METHANE-MONITORING SYSTEMS
  5. Subpart A—General Provisions

The date of receipt of an application will determine the order of precedence for investigation and testing. The applicant will be notified of the date on which tests will begin.

Note:

If an assembly, subassembly, or component fails to meet any of the requirements, testing of it may be suspended and other items may be tested. However, if the cause of failure is corrected, testing will be resumed after completing such other test work as may be in progress.