30 CFR 285.614: When may I begin conducting activities under my approved SAP?

Read at publisher ↗
Where this section sits in the code
  1. Title 30—Mineral Resources
  2. CHAPTER II—BUREAU OF SAFETY AND ENVIRONMENTAL ENFORCEMENT, DEPARTMENT OF THE INTERIOR
  3. SUBCHAPTER B—OFFSHORE
  4. PART 285—RENEWABLE ENERGY AND ALTERNATE USES OF EXISTING FACILITIES ON THE OUTER CONTINENTAL SHELF
  5. Subpart F—Information Requirements

(a) You may begin conducting the activities approved in your SAP following BOEM approval of your SAP.

(b) If you are installing a facility or a combination of facilities deemed by BOEM to be complex or significant, as provided in 30 CFR 585.613(a)(1), you must comply with the requirements of subpart G of this part and submit the Safety Management System (SMS) description required by § 285.810 before construction may begin.