30 CFR 285.636: What notices must I provide BSEE following approval of my COP?

Read at publisher ↗
Where this section sits in the code
  1. Title 30—Mineral Resources
  2. CHAPTER II—BUREAU OF SAFETY AND ENVIRONMENTAL ENFORCEMENT, DEPARTMENT OF THE INTERIOR
  3. SUBCHAPTER B—OFFSHORE
  4. PART 285—RENEWABLE ENERGY AND ALTERNATE USES OF EXISTING FACILITIES ON THE OUTER CONTINENTAL SHELF
  5. Subpart F—Information Requirements

You must notify BSEE in writing of the following events, within the time periods provided:

(a) No later than 30 days after commencing activities associated with the placement of facilities on the lease area under a Fabrication and Installation Report.

(b) No later than 30 days after completion of construction and installation activities under a Fabrication and Installation Report.

(c) At least 7 days before commencing commercial operations.