30 CFR 285.636: What notices must I provide BSEE following approval of my COP?
Where this section sits in the code
- Title 30—Mineral Resources
- CHAPTER II—BUREAU OF SAFETY AND ENVIRONMENTAL ENFORCEMENT, DEPARTMENT OF THE INTERIOR
- SUBCHAPTER B—OFFSHORE
- PART 285—RENEWABLE ENERGY AND ALTERNATE USES OF EXISTING FACILITIES ON THE OUTER CONTINENTAL SHELF
- Subpart F—Information Requirements
You must notify BSEE in writing of the following events, within the time periods provided:
(a) No later than 30 days after commencing activities associated with the placement of facilities on the lease area under a Fabrication and Installation Report.
(b) No later than 30 days after completion of construction and installation activities under a Fabrication and Installation Report.
(c) At least 7 days before commencing commercial operations.
Collected 2026-08-27T02:25:24Z. Source file · JSON