30 CFR 285.905: When must I submit my decommissioning application?
Where this section sits in the code
- Title 30—Mineral Resources
- CHAPTER II—BUREAU OF SAFETY AND ENVIRONMENTAL ENFORCEMENT, DEPARTMENT OF THE INTERIOR
- SUBCHAPTER B—OFFSHORE
- PART 285—RENEWABLE ENERGY AND ALTERNATE USES OF EXISTING FACILITIES ON THE OUTER CONTINENTAL SHELF
- Subpart I—Decommissioning
You must submit your decommissioning application upon the earliest of the following dates:
(a) Two (2) years before the expiration of your lease.
(b) Ninety (90) days after completion of your commercial activities on a commercial lease.
(c) Ninety (90) days after completion of your approved activities under a limited lease on a ROW grant or RUE grant.
(d) Ninety (90) days after cancellation, relinquishment, or other termination of your lease or grant.
(e) Ninety (90) calendar days after BSEE determines a facility is no longer useful for operations.