GroundRules
← Search the law
Federal regulations · Through 2026-08-25 · Newer source version available

30 CFR 285.912: After I remove a facility, cable, or pipeline, what information must I submit?

Read at publisher ↗
Where this section sits in the code
  1. Title 30—Mineral Resources
  2. CHAPTER II—BUREAU OF SAFETY AND ENVIRONMENTAL ENFORCEMENT, DEPARTMENT OF THE INTERIOR
  3. SUBCHAPTER B—OFFSHORE
  4. PART 285—RENEWABLE ENERGY AND ALTERNATE USES OF EXISTING FACILITIES ON THE OUTER CONTINENTAL SHELF
  5. Subpart I—Decommissioning

Within 60 days after you remove a facility, cable, or pipeline, you must submit a written report to BSEE that includes the following:

(a) A summary of the removal activities, including the date they were completed;

(b) A description of any mitigation measures you took; and

(c) If you used explosives, a statement signed by your authorized representative that certifies that the types and amount of explosives you used in removing the facility were consistent with those in the approved decommissioning application.

Collected 2026-08-27T02:25:24Z. Source file · JSON

Browse this collection