32 CFR 37.905: Must I make receipt of the final performance report a condition for final payment?

Read at publisher ↗
Where this section sits in the code
  1. Title 32—National Defense
  2. Subtitle A—Department of Defense
  3. CHAPTER I—OFFICE OF THE SECRETARY OF DEFENSE
  4. SUBCHAPTER C—DoD GRANT AND AGREEMENT REGULATIONS
  5. PART 37—TECHNOLOGY INVESTMENT AGREEMENTS
  6. Subpart G—Award Terms Related to Other Administrative Matters

If a final report is required, your TIA should make receipt of the report a condition for final payment. If the payments are based on payable milestones, the submission and acceptance of the final report by the Government representative will be incorporated as an event that is a prerequisite for one of the payable milestones.