33 CFR 150.445: When is oil in a single point mooring-oil transfer system (SPM-OTS) displaced with water?
Where this section sits in the code
- Title 33—Navigation and Navigable Waters
- CHAPTER I—COAST GUARD, DEPARTMENT OF HOMELAND SECURITY
- SUBCHAPTER NN—DEEPWATER PORTS
- PART 150—DEEPWATER PORTS: OPERATIONS
- Subpart E—Cargo Transfer Operations
(a) The oil in an SPM-OTS must be displaced with water, and the valve at the pipeline end manifold must be closed whenever:
(1) A storm warning forecasts weather conditions that will exceed the design operating criteria listed in the operations manual for the SPM-OTS;
(2) A vessel is about to depart the SPM because of storm conditions; or
(3) The SPM is not scheduled for use in an oil transfer operation within the next 7 days.
(b) The requirement in paragraph (a) of this section is waived if port officials can demonstrate to the Sector Commander, or MSU Commander, with COTP and OCMI authority that a satisfactory alternative means of safely securing all cargo transfer hoses can be implemented in the event of severe weather conditions.