36 CFR 52.18: When must the selected respondent execute the contract?
Where this section sits in the code
- Title 36—Parks, Forests, and Public Property
- CHAPTER I—NATIONAL PARK SERVICE, DEPARTMENT OF THE INTERIOR
- PART 52—VISITOR EXPERIENCE IMPROVEMENTS AUTHORITY CONTRACTS
- Subpart B—Solicitation, Selection, and Award Procedures
The selected respondent must execute the contract within the time period established by the Director. If the selected respondent fails to execute the contract in this period, the Director may select another responsive response and enter into negotiations with that respondent, or may cancel the solicitation and choose to resolicit the contract.
Collected 2026-08-27T02:25:44Z. Source file · JSON