40 CFR 60.2141: By what date must I conduct the initial air pollution control device inspection?

Read at publisher ↗
Where this section sits in the code
  1. Title 40—Protection of Environment
  2. CHAPTER I—ENVIRONMENTAL PROTECTION AGENCY
  3. SUBCHAPTER C—AIR PROGRAMS
  4. PART 60—STANDARDS OF PERFORMANCE FOR NEW STATIONARY SOURCES
  5. Subpart CCCC—Standards of Performance for Commercial and Industrial Solid Waste Incineration Units

(a) The initial air pollution control device inspection must be conducted within 60 days after installation of the control device and the associated CISWI reaches the charge rate at which it will operate, but no later than 180 days after the device's initial startup.

(b) Within 10 operating days following an air pollution control device inspection, all necessary repairs must be completed unless the owner or operator obtains written approval from the state agency establishing a date whereby all necessary repairs of the designated facility must be completed.