40 CFR 60.2891: Do all components of these new source performance standards apply at the same time?
Where this section sits in the code
- Title 40—Protection of Environment
- CHAPTER I—ENVIRONMENTAL PROTECTION AGENCY
- SUBCHAPTER C—AIR PROGRAMS
- PART 60—STANDARDS OF PERFORMANCE FOR NEW STATIONARY SOURCES
- Subpart EEEE—Standards of Performance for Other Solid Waste Incineration Units
No, you must meet the preconstruction siting analysis and waste management plan requirements before you commence construction, reconstruction, or modification of the OSWI unit. The operator training and qualification, emission limitations, operating limits, performance testing and compliance, monitoring, and most recordkeeping and reporting requirements are met after the OSWI unit begins operation.
Collected 2026-08-27T02:26:04Z. Source file · JSON