40 CFR 60.2928: By what date must I conduct the initial performance test?

Read at publisher ↗
Where this section sits in the code
  1. Title 40—Protection of Environment
  2. CHAPTER I—ENVIRONMENTAL PROTECTION AGENCY
  3. SUBCHAPTER C—AIR PROGRAMS
  4. PART 60—STANDARDS OF PERFORMANCE FOR NEW STATIONARY SOURCES
  5. Subpart EEEE—Standards of Performance for Other Solid Waste Incineration Units

The initial performance test must be conducted within 60 days after your OSWI unit reaches the charge rate at which it will operate, but no later than 180 days after its initial startup. For units which start-up between August 31, 2020, and December 29, 2025, the initial performance test must be conducted within 60 days after your OSWI unit reaches the charge rate at which it will operate, but no later than 180 days after its initial startup, or by February 25, 2026, whichever date is later.

Collected 2026-08-27T02:26:04Z. Source file · JSON

Browse this collection