40 CFR 60.6330: What are my requirements for meeting increments of progress and achieving final compliance?
Where this section sits in the code
- Title 40—Protection of Environment
- CHAPTER I—ENVIRONMENTAL PROTECTION AGENCY
- SUBCHAPTER C—AIR PROGRAMS
- PART 60—STANDARDS OF PERFORMANCE FOR NEW STATIONARY SOURCES
- Subpart WWWW—Emission Guidelines and Compliance Times for Large Municipal Waste Combustors Constructed on or Before January 23, 2024
If you plan to achieve compliance more than 1 year but less than 3 years following the effective date of state plan approval and a permit modification is not required, or more than 1 year but less than 3 years following the date of issuance of a revised construction or operation permit if a permit modification is required, you must meet five increments of progress:
(a) Submit a final control plan.
(b) Submit a notification of retrofit contract award.
(c) Initiate onsite construction.
(d) Complete onsite construction.
(e) Achieve final compliance.