40 CFR Table 1 to Subpart MMMM of Part 60: Table 1 to Subpart MMMM of Part 60—Model Rule—Increments of Progress and Compliance Schedules for Existing Sewage Sludge Incineration Units
Where this section sits in the code
- Title 40—Protection of Environment
- CHAPTER I—ENVIRONMENTAL PROTECTION AGENCY
- SUBCHAPTER C—AIR PROGRAMS
- PART 60—STANDARDS OF PERFORMANCE FOR NEW STATIONARY SOURCES
- Subpart MMMM—Emission Guidelines and Compliance Times for Existing Sewage Sludge Incineration Units
Comply with these increments of progress By these dates a
Increment 1—Submit final control plan (Dates to be specified in state plan)
Increment 2—Final compliance (Dates to be specified in state plan) b
a Site-specific schedules can be used at the discretion of the state.
b The date can be no later than 3 years after the effective date of state plan approval or March 21, 2016 for SSI units that commenced construction on or before October 14, 2010.