40 CFR Table 7 to Subpart AAAAA of Part 63: Table 7 to Subpart AAAAA of Part 63—Periodic Monitoring for Compliance With Opacity and Visible Emissions Limits

Read at publisher ↗
Where this section sits in the code
  1. Title 40—Protection of Environment
  2. CHAPTER I—ENVIRONMENTAL PROTECTION AGENCY
  3. SUBCHAPTER C—AIR PROGRAMS
  4. PART 63—NATIONAL EMISSION STANDARDS FOR HAZARDOUS AIR POLLUTANTS FOR SOURCE CATEGORIES
  5. Subpart AAAAA—National Emission Standards for Hazardous Air Pollutants for Lime Manufacturing Plants

As required in § 63.7121 you must periodically demonstrate compliance with each opacity and VE limit that applies to you, according to the following table:

For . . . For the following emission limitation . . . You must demonstrate ongoing compliance . . .

1. Each PSH operation subject to an opacity limitation as required in Table 1 to this subpart, or any vents from buildings subject to an opacity limitation a. 7-10 percent opacity, depending on the PSH operation, as required in Table 1 to this subpart (i) Conducting a monthly 1-minute VE check of each emission unit in accordance with § 63.7121(e); the check must be conducted while the affected source is in operation; (ii) If no VE are observed in 6 consecutive monthly checks for any emission unit, you may decrease the frequency of VE checking from monthly to semi-annually for that emission unit; if VE are observed during any semiannual check, you must resume VE checking of that emission unit on a monthly basis and maintain that schedule until no VE are observed in 6 consecutive monthly checks;

(iii) If no VE are observed during the semiannual check for any emission unit, you may decrease the frequency of VE checking from semi-annually to annually for that emission unit; if VE are observed during any annual check, you must resume VE checking of that emission unit on a monthly basis and maintain that schedule until no VE are observed in 6 consecutive monthly checks; and

(iv) If VE are observed during any VE check, you must conduct a 6-minute test of opacity in accordance with Method 9 of appendix A to part 60 of this chapter; you must begin the Method 9 test within 1 hour of any observation of VE and the 6-minute opacity reading must not exceed the applicable opacity limit.

2. Any building subject to a VE limit, according to item 8 of Table 1 to this subpart a. No VE (i) Conducting a monthly VE check of the building, in accordance with the specifications in § 63.7112(k); the check must be conducted while all the enclosed PSH operations are operating;

(ii) The check for each affected building must be at least 5 minutes, with each side of the building and roof being observed for at least 1 minute;

(iii) If no VE are observed in 6 consecutive monthly checks of the building, you may decrease the frequency of checking from monthly to semi-annually for that affected source; if VE are observed during any semi-annual check, you must resume checking on a monthly basis and maintain that schedule until no VE are observed in 6 consecutive monthly checks; and

(iv) If no VE are observed during the semi-annual check, you may decrease the frequency of checking from semi-annually to annually for that affected source; and if VE are observed during any annual check, you must resume checking of that emission unit on a monthly basis and maintain that schedule until no VE are observed in 6 consecutive monthly checks (the source is in compliance if no VE are observed during any of these checks).