42 CFR 495.340: As-needed HIT PAPD update and as-needed HIT IAPD update requirements.
Where this section sits in the code
- Title 42—Public Health
- CHAPTER IV—CENTERS FOR MEDICARE & MEDICAID SERVICES, DEPARTMENT OF HEALTH AND HUMAN SERVICES
- SUBCHAPTER G—STANDARDS AND CERTIFICATION
- PART 495—STANDARDS FOR THE ELECTRONIC HEALTH RECORD TECHNOLOGY INCENTIVE PROGRAM
- Subpart D—Requirements Specific to the Medicaid Program
Each State must submit a HIT PAPD update or a HIT IAPD no later than 60 days after the occurrence of project changes including but not limited to any of the following:
(a) A projected cost increase of $100,000 or more.
(b) A schedule extension of more than 60 days for major milestones.
(c) A significant change in planning approach or implementation approach, or scope of activities beyond that approved in the HIT planning advance planning document or the HIT implementation advance planning document.
(d) A change in implementation concept or a change to the scope of the project.
(e) A change to the approved cost allocation methodology.
Collected 2026-08-27T02:26:11Z. Source file · JSON