43 CFR 3261.11: How do I apply for approval of drilling operations and well pad construction?

Read at publisher ↗
Where this section sits in the code
  1. Title 43—Public Lands: Interior
  2. Subtitle B—Regulations Relating to Public Lands
  3. CHAPTER II—BUREAU OF LAND MANAGEMENT, DEPARTMENT OF THE INTERIOR
  4. SUBCHAPTER C—MINERALS MANAGEMENT (3000)
  5. PART 3200—GEOTHERMAL RESOURCE LEASING
  6. Subpart 3261—Drilling Operations: Getting a Permit

(a) Send to BLM:

(1) A completed and signed drilling permit application, Form 3260-2;

(2) A complete operations plan (§ 3261.12);

(3) A complete drilling program (§ 3261.13); and

(4) An acceptable bond (§ 3261.18).

(b) Do not start any drilling operations until after BLM approves the permit.