43 CFR 3282.3: When must the unit operator submit an application for BLM approval of a proposed initial participating area?

Read at publisher ↗
Where this section sits in the code
  1. Title 43—Public Lands: Interior
  2. Subtitle B—Regulations Relating to Public Lands
  3. CHAPTER II—BUREAU OF LAND MANAGEMENT, DEPARTMENT OF THE INTERIOR
  4. SUBCHAPTER C—MINERALS MANAGEMENT (3000)
  5. PART 3280—GEOTHERMAL RESOURCES UNIT AGREEMENTS
  6. Subpart 3282—Participating Area

The unit operator must submit an application for BLM approval of a proposed participating area no later than:

(a) 60 days after receiving BLM's determination identified in § 3281.15(a)(3) that a unit well will produce or utilize in commercial quantities; or

(b) 30 days before the initiation of commercial operations, whichever occurs earlier.