43 CFR 3282.3: When must the unit operator submit an application for BLM approval of a proposed initial participating area?
Where this section sits in the code
- Title 43—Public Lands: Interior
- Subtitle B—Regulations Relating to Public Lands
- CHAPTER II—BUREAU OF LAND MANAGEMENT, DEPARTMENT OF THE INTERIOR
- SUBCHAPTER C—MINERALS MANAGEMENT (3000)
- PART 3280—GEOTHERMAL RESOURCES UNIT AGREEMENTS
- Subpart 3282—Participating Area
The unit operator must submit an application for BLM approval of a proposed participating area no later than:
(a) 60 days after receiving BLM's determination identified in § 3281.15(a)(3) that a unit well will produce or utilize in commercial quantities; or
(b) 30 days before the initiation of commercial operations, whichever occurs earlier.