43 CFR 3809.21: When do I have to submit a notice?
Where this section sits in the code
- Title 43—Public Lands: Interior
- Subtitle B—Regulations Relating to Public Lands
- CHAPTER II—BUREAU OF LAND MANAGEMENT, DEPARTMENT OF THE INTERIOR
- SUBCHAPTER C—MINERALS MANAGEMENT (3000)
- PART 3800—MINING CLAIMS UNDER THE GENERAL MINING LAWS
- Subpart 3809—Surface Management
(a) You must submit a complete notice of your operations 15 calendar days before you commence exploration causing surface disturbance of 5 acres or less of public lands on which reclamation has not been completed. See § 3809.301 for information on what you must include in your notice.
(b) You must not segment a project area by filing a series of notices for the purpose of avoiding filing a plan of operations. See §§ 3809.300 through 3809.336 for regulations applicable to notice-level operations.