43 CFR 404.50: What information will be included in the feasibility report prepared by Reclamation.

Read at publisher ↗
Where this section sits in the code
  1. Title 43—Public Lands: Interior
  2. Subtitle B—Regulations Relating to Public Lands
  3. CHAPTER I—BUREAU OF RECLAMATION, DEPARTMENT OF THE INTERIOR
  4. PART 404—RECLAMATION RURAL WATER SUPPLY PROGRAM
  5. Subpart D—Feasibility Studies

The feasibility report prepared by Reclamation will include:

(a) Reclamation's finding as to whether the proposed rural water supply project is feasible and the reasons supporting that determination;

(b) A recommendation to Congress regarding whether or not the proposed rural water supply project should be authorized for construction, and the reasons supporting the recommendation. This recommendation will be based on Reclamation's review of the feasibility study and its application of the criteria set forth in § 404.49; and

(c) If the rural water supply project is recommended for construction, the feasibility report will also include:

(1) The appropriate Federal and non-Federal share of the capital construction costs for the project and for projects involving multiple project sponsors, the portion of those costs allocated to each project sponsor;

(2) What amount of grants, loan guarantees, or combination of grants and loan guarantees should constitute the Federal share of the project;

(3) The annual operation, maintenance, and replacement costs, and the portion of those costs allocated to each project sponsor participating in the rural water supply project; and

(4) An assessment of the financial capability of each project sponsor participating in the rural water supply project to pay the portion of the construction and operation, maintenance, and replacement costs allocated to it.