43 CFR 45.50: When and where will the hearing be held?
Where this section sits in the code
- Title 43—Public Lands: Interior
- Subtitle A—Office of the Secretary of the Interior
- PART 45—CONDITIONS AND PRESCRIPTIONS IN FERC HYDROPOWER LICENSES
- Subpart B—Hearing Process
(a) Except as provided in paragraph (b) of this section, the hearing will be held at the time and place set at the initial prehearing conference under § 45.40, generally within 25 days after the date set for completion of discovery.
(b) On motion by a party or on the ALJ's initiative, the ALJ may change the date, time, or place of the hearing if he or she finds:
(1) That there is good cause for the change; and
(2) That the change will not unduly prejudice the parties and witnesses.