46 CFR 159.007-5: -5 Production inspections and tests: Application for acceptance.
Where this section sits in the code
- Title 46—Shipping
- CHAPTER I—COAST GUARD, DEPARTMENT OF HOMELAND SECURITY
- SUBCHAPTER Q—EQUIPMENT, CONSTRUCTION, AND MATERIALS: SPECIFICATIONS AND APPROVAL
- PART 159—APPROVAL OF EQUIPMENT AND MATERIALS
- Subpart 159.007—Production Inspection and Tests of Approved Equipment and Materials
(a) If the applicable subpart requires production inspections and tests by an independent laboratory, the manufacturer must select a laboratory and submit an application for acceptance that meets § 159.010-5(a) unless the laboratory—
(1) Is listed in the subpart; or
(2) Is accepted by the Commandant for approval inspections and tests of the equipment or material under § 159.005-7(a)(1).
(b) If the manufacturer wants to follow the laboratory's procedures for production inspections and tests instead of meeting the Coast Guard procedures under this subchapter, the application must contain a description of those procedures.