46 CFR 160.170-23: -23 Procedure for approval of design, material, or construction change.
Where this section sits in the code
- Title 46—Shipping
- CHAPTER I—COAST GUARD, DEPARTMENT OF HOMELAND SECURITY
- SUBCHAPTER Q—EQUIPMENT, CONSTRUCTION, AND MATERIALS: SPECIFICATIONS AND APPROVAL
- PART 160—LIFESAVING EQUIPMENT
- Subpart 160.170—Davit-Launched Liferaft Automatic Release Hooks (SOLAS)
(a) Each change in design, material, or construction from the plans approved under 46 CFR 159.005-13 and § 160.170-13(h) of this subpart must be approved by the Commandant before being used in any production release mechanism. The manufacturer must submit any such change following the procedures in § 160.170-9 of this subpart, but documentation on items that are unchanged from the plans approved under 46 CFR 159.005-13 and § 160.170-13(h) of this subpart need not be resubmitted.
(b) Unless determined by the Commandant to be unnecessary, a prototype release mechanism with each change described in paragraph (a) of this section must be made and tested according to the procedures for new approvals in §§ 160.170-9 through 160.170-13 of this subpart.
(c) Determinations of equivalence of design, construction, and materials will be made by the Commandant only.