46 CFR 52.01-100: -100 Openings and compensation (modifies PG-32 through PG-39, PG-42 through PG-55).
Where this section sits in the code
- Title 46—Shipping
- CHAPTER I—COAST GUARD, DEPARTMENT OF HOMELAND SECURITY
- SUBCHAPTER F—MARINE ENGINEERING
- PART 52—POWER BOILERS
- Subpart 52.01—General Requirements
(a) The rules for openings and compensation must be as indicated in PG-32 through PG-55 of Section I of the ASME BPVC (incorporated by reference; see § 52.01-1) except as noted otherwise in this section.
(b) (Modifies PG-39.) Pipe and nozzle necks must be attached to vessel walls as indicated in PG-39 of Section I of the ASME BPVC except that threaded connections must not be used under any of the following conditions:
(c) (Modifies PG-42.) Butt-welding flanges and fittings must be used when full radiography is required by § 56.95-10 of this subchapter.
Collected 2026-08-27T02:26:22Z. Source file · JSON