46 CFR 61.05-5: -5 Preparation of boilers for inspection and test.
Where this section sits in the code
- Title 46—Shipping
- CHAPTER I—COAST GUARD, DEPARTMENT OF HOMELAND SECURITY
- SUBCHAPTER F—MARINE ENGINEERING
- PART 61—PERIODIC TESTS AND INSPECTIONS
- Subpart 61.05—Tests and Inspections of Boilers
(a) For internal inspection, manhole and handhold plates, and washout plugs must be removed as required by the marine inspector and the furnace and combustion chambers must be thoroughly cooled and cleaned.
(b) In preparing the boilers for the hydrostatic test, they must be filled with water at not less than 70 °F and not more than 160 °F for watertube boilers, and not more than 100 °F for firetube boilers. The safety valves must be secured by means of gags or clamps.