48 CFR 1830.7002-1: 1830.7002-1 Definitions.
Where this section sits in the code
- Title 48—Federal Acquisition Regulations System
- CHAPTER 18—NATIONAL AERONAUTICS AND SPACE ADMINISTRATION
- SUBCHAPTER E—GENERAL CONTRACTING REQUIREMENTS
- PART 1830—COST ACCOUNTING STANDARDS ADMINISTRATION
- Subpart 1830.70—Facilities Capital Employed for Facilities in Use and For Facilities Under Construction
(a) Cost of money rate is either—
(1) The interest rate determined by the Secretary of the Treasury under Public Law 92-41 (85 Stat. 97); or
(2) The time-weighted average of such rates for each cost accounting period during which the capital asset is being constructed, fabricated, or developed.
(b) Representative investment is the calculated amount considered invested by the contractor during the cost accounting period to construct, fabricate, or develop the capital asset.
Collected 2026-08-27T02:26:29Z. Source file · JSON