48 CFR 1852.232-79: 1852.232-79 Payment for on-site preparatory costs.
Where this section sits in the code
- Title 48—Federal Acquisition Regulations System
- CHAPTER 18—NATIONAL AERONAUTICS AND SPACE ADMINISTRATION
- SUBCHAPTER H—CLAUSES AND FORMS
- PART 1852—SOLICITATION PROVISIONS AND CONTRACT CLAUSES
- Subpart 1852.2—Texts of Provisions and Clauses
As prescribed in 1832.111-70, insert the following clause:
Payment for On-Site Preparatory Costs (SEP 1987)
Costs associated with on-site preparatory work (start-up or set-up costs) will be prorated over all work activities of a Critical Path Method (CPM) network or Progress Chart against which progress payments will be sought. Separate payment for on-site preparatory costs will not be made by the Government.
(End of clause)
Collected 2026-08-27T02:26:29Z. Source file · JSON