48 CFR 217.7403: 217.7403 Policy.
Where this section sits in the code
- Title 48—Federal Acquisition Regulations System
- CHAPTER 2—DEFENSE ACQUISITION REGULATIONS SYSTEM, DEPARTMENT OF DEFENSE
- SUBCHAPTER C—CONTRACTING METHODS AND CONTRACT TYPES
- PART 217—SPECIAL CONTRACTING METHODS
- Subpart 217.74—Undefinitized Contract Actions
DoD policy is that undefinitized contract actions shall—
(a) Be used only when—
(1) The negotiation of a definitive contract action is not possible in sufficient time to meet the Government's requirements; and
(2) The Government's interest demands that the contractor be given a binding commitment so that contract performance can begin immediately.
(b) Be as complete and definite as practicable under the particular circumstances.