48 CFR 536.7107: 536.7107 Contract clauses (FAR DEVIATION).

Read at publisher ↗
Where this section sits in the code
  1. Title 48—Federal Acquisition Regulations System
  2. CHAPTER 5—GENERAL SERVICES ADMINISTRATION
  3. SUBCHAPTER F—SPECIAL CATEGORIES OF CONTRACTING
  4. PART 536—CONSTRUCTION AND ARCHITECT-ENGINEER CONTRACTS
  5. Subpart 536.71—Construction-Manager-as-Constructor Contracting

(a) FAR deviation. GSA has a deviation from FAR 52.216-17 that allows use of the clause 552.236-79 in lieu of the FAR clause at 52.216-17. Insert a clause substantially the same as the clause at 552.236-79, Construction-Manager-As-Constructor, in solicitations and contracts if construction, dismantling, or removal of improvements is contemplated when a CMc project delivery method will be followed in lieu of the FAR clause at 52.216-17.

(b) Insert a clause substantially the same as the clause at 552.236-80, Accounting Records and Progress Payments, in solicitations and contracts if construction, dismantling, or removal of improvements is contemplated when a CMc project delivery method will be followed and cost accounting standards do not apply. This clause is used when the clauses at FAR 52.230-2 Cost Accounting Standards, FAR 52.230-3 Disclosure and Consistency of Cost Accounting Practices, and FAR 52.230-6 Administration of Cost Accounting Standards do not apply.