49 CFR 192.329: Installation of plastic pipelines by trenchless excavation.
Where this section sits in the code
- Title 49—Transportation
- Subtitle B—Other Regulations Relating to Transportation
- CHAPTER I—PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION, DEPARTMENT OF TRANSPORTATION
- SUBCHAPTER D—PIPELINE SAFETY
- PART 192—TRANSPORTATION OF NATURAL AND OTHER GAS BY PIPELINE: MINIMUM FEDERAL SAFETY STANDARDS
- Subpart G—General Construction Requirements for Transmission Lines and Mains
Plastic pipelines installed by trenchless excavation must comply with the following:
(a) Each operator must take practicable steps to provide sufficient clearance for installation and maintenance activities from other underground utilities and/or structures at the time of installation.
(b) For each pipeline section, plastic pipe and components that are pulled through the ground must use a weak link, as defined by § 192.3, to ensure the pipeline will not be damaged by any excessive forces during the pulling process.
Collected 2026-08-27T02:26:34Z. Source file · JSON