49 CFR 633.23: FTA review of a project management plan.
Where this section sits in the code
- Title 49—Transportation
- Subtitle B—Other Regulations Relating to Transportation
- CHAPTER VI—FEDERAL TRANSIT ADMINISTRATION, DEPARTMENT OF TRANSPORTATION
- PART 633—PROJECT MANAGEMENT OVERSIGHT
- Subpart C—Project Management Plans
Within 60 days of receipt of a project management plan, the Administrator will notify the recipient that:
(a) The plan is approved;
(b) The plan is disapproved, including the reasons for the disapproval;
(c) The plan will require modification, as specified, before approval; or
(d) The Administrator has not yet completed review of the plan, and state when it will be reviewed.
Collected 2026-08-27T02:26:34Z. Source file · JSON