49 CFR 633.23: FTA review of a project management plan.

Read at publisher ↗
Where this section sits in the code
  1. Title 49—Transportation
  2. Subtitle B—Other Regulations Relating to Transportation
  3. CHAPTER VI—FEDERAL TRANSIT ADMINISTRATION, DEPARTMENT OF TRANSPORTATION
  4. PART 633—PROJECT MANAGEMENT OVERSIGHT
  5. Subpart C—Project Management Plans

Within 60 days of receipt of a project management plan, the Administrator will notify the recipient that:

(a) The plan is approved;

(b) The plan is disapproved, including the reasons for the disapproval;

(c) The plan will require modification, as specified, before approval; or

(d) The Administrator has not yet completed review of the plan, and state when it will be reviewed.