7 CFR 1726.150: Headquarters buildings.

Read at publisher ↗
Where this section sits in the code
  1. Title 7—Agriculture
  2. Subtitle B—Regulations of the Department of Agriculture
  3. CHAPTER XVII—RURAL UTILITIES SERVICE, DEPARTMENT OF AGRICULTURE
  4. PART 1726—ELECTRIC SYSTEM CONSTRUCTION POLICIES AND PROCEDURES
  5. Subpart E—Buildings

This section includes headquarters buildings such as warehouses and equipment service type buildings. Generating plant buildings are covered under subpart D of this part.

(a) Contract forms. The borrower must use RUS Form 257, Contract to Construct Buildings, for all contracts for construction of new headquarters facilities, and additions to, or modifications of existing headquarters facilities (except for minor modifications or improvements).

(b) Procurement procedures. A borrower may use Multiparty Lump Sum Quotations to award contracts in amounts of up to a cumulative total of $1,500,000 or four percent of NUP, whichever is greater, per calendar year of headquarters construction (including minor modifications or improvements). The borrower shall use formal competitive bidding for all other headquarters contract construction unless RUS specifically approves an alternative method.

(c) Contract approval. Contracts for headquarters construction are not subject to RUS approval and need not be submitted to RUS unless specifically requested by RUS on a case by case basis.