30 ILCS 538/1-55: Transition to design-bid-build.
Where this section sits in the code
- CHAPTER 30 FINANCE
- Progressive Design-Build Pilot Program Act.
(Section scheduled to be repealed on January 1, 2028)
At the completion of design development, the progressive design-build entity must provide a firm fixed price. The State construction agency reserves the right to transition the project to the design-bid-build method if the fixed price exceeds the project budget, the progressive design-build entity's proposed schedule is unreasonable, or if transitioning to the design-bid-build method is in the best interests of the State.