30 ILCS 557/15: Arbitration.
Where this section sits in the code
- CHAPTER 30 FINANCE
- Public Construction Contract Act.
A contractor and governmental entity may, by mutual agreement, arbitrate the contractor's entitlement to recover the actual increase in contract time or costs incurred because of a physical condition at the site. The judgment rendered may be entered in any court having jurisdiction over the matter.