70 ILCS 860/30: Small projects.
Where this section sits in the code
- CHAPTER 70 SPECIAL DISTRICTS
- Forest Preserve District and Conservation District Design-Build Authorization Act.
In any case where the total overall cost of the project is estimated to be less than $12,000,000, the forest preserve or conservation district may combine the two-phase procedure for selection described in Section 25 into one combined step, provided that all the requirements of evaluation are performed in accordance with Section 25.