IC 8-1-7.9-12: "Planning costs"
Where this section sits in the code
- TITLE 8. UTILITIES AND TRANSPORTATION
- ARTICLE 1. UTILITIES GENERALLY
- Chapter 7.9. Expedited Generation Resource Plans and Large Load Customers
Sec. 12. (a) As used in this chapter, "planning costs" means costs:
(1) incurred or to be incurred by an energy utility before the issuance of an order by the commission under this chapter; and
(2) related to an acquisition or project.
(b) The term includes study, analysis, pre-engineering, engineering, legal, financing, and regulatory costs.