IC 8-1-7.9-25: Commission's review of energy utility's estimated acquisition costs or project costs; recovery of costs
Where this section sits in the code
- TITLE 8. UTILITIES AND TRANSPORTATION
- ARTICLE 1. UTILITIES GENERALLY
- Chapter 7.9. Expedited Generation Resource Plans and Large Load Customers
Sec. 25. (a) The commission shall review an energy utility's:
(1) estimated acquisition costs submitted under section 20(c)(1)(D) of this chapter; or
(2) estimated project costs filed under section 23(b)(1)(D) of this chapter;
as applicable.
(b) If the commission approves, with or without modification, an energy utility's generation resource submittal or petition for approval of a project, the energy utility may recover:
(1) acquisition costs; or
(2) project costs;
as applicable, that have been reviewed and found reasonable by the commission, with a return at the energy utility's weighted average cost of capital.
(c) If the commission denies an energy utility's generation resource submittal or petition for approval of a project, the energy utility may recover planning costs that have been reviewed and found reasonable by the commission, without a return.
(d) Absent fraud, concealment, or gross mismanagement, an energy utility may recover:
(1) acquisition costs; or
(2) project costs;
as applicable, with a return at the energy utility's weighted average cost of capital, that the energy utility has incurred or contractually will incur in reliance on a commission order issued under this chapter.
Collected 2026-10-04T20:08:46Z. Source file · JSON