KRS 353.415: Carbon dioxide sequestration facility permit requirements -- Application
Where this section sits in the code
- KRS Chapter 353
of KRS 353.411 to 353.459.
(1) A person shall not construct or operate a carbon dioxide sequestration facility
without first securing a:
(a) Class VI underground injecti on control permit from the US EPA or the
cabinet; and
(b) Drilling permit issued by the cabinet.
(2) The injection of carbon dioxide for purposes of enhancing the recovery of oil or
natural gas pursuant to a permit approved by the cabinet under KRS 353.592 shall
not be subject to the provisions of KRS 353.411 to 353.459.
(3) If an oil, natural gas, or coalbed methane well operator proposes to convert its
operations to carbon dioxide sequestration, then the underground carbon dioxide
sequestration facility shall be regulated pursuant to KRS 353.411 to 353.459.
Collected 2026-09-05T20:58:39Z. Source file · JSON