KRS 353.421: Technical review of applications -- Duties of cabinet.
Where this section sits in the code
- KRS Chapter 353
(1) Within sixty (60) calendar days of receiving an application for a Class VI
underground injection control well, the cabinet shall provide written notice to the
applicant as to the administrative completeness of the application. If the application
is determined to be administratively:
(a) Complete, the cabinet shall notify the applicant in writing that the technical
review period provided by subsection (2) of this section has begun; or
(b) Incomplete, the cabinet shall notify the applicant of the deficiencies that
render it administratively incomplete. The applicant shall have thirty (30)
calendar days from receiving the cabinet's notice of deficiency to correct the
deficiencies and render the application administratively complete.
(2) (a) Technical review of an application shall begin when the cabinet has deemed
the application administratively complete and ready for review. The cabinet
shall issue a final determination to either approve or deny the application
within three hundred sixty -five (365) calendar da ys from the date an
administrative completeness determination has been made by the cabinet.
(b) If the application is found deficient during technical review, the cabinet shall
notify the applicant in writing of the deficiencies identified by the cabinet
during the review. The applicant shall respond to the deficiencies with
information that addresses the identified deficiencies.
(3) An application shall be considered temporarily withdrawn when an applicant is
correcting deficiencies noted by the cabinet pu rsuant to subsection (1)(b) or (2)(b)
of this section. Periods of temporary withdrawal shall not be counted against the
review period allotted to the cabinet for administrative or technical review. Upon
resubmittal the review period allotted to the cabinet shall resume.