Md. Code, Public Safety § 12–605
Where this section sits in the code
- Article - Public Safety
(a) Before a utility authorizes electrical current to be turned on for a premise or structure, the utility must receive a cut–in certificate from a certified nongovernmental electrical inspector or governmental unit that is qualified to issue electrical inspection certificates.
(b) Within 15 days after completion, each electrical installation shall be certified by a certified nongovernmental electrical inspector or a governmental unit that is qualified to issue electrical inspection certificates.
Collected 2026-09-14T20:00:18Z. Source file · JSON