Mich. Comp. Laws § 460.1333: Bonding requirements; limitations.
Where this section sits in the code
- MI Code
- Chapter 460
- Act Act-365-of-2018
Sec. 33.
(1) As a condition of a permit described in this act, an authority may adopt bonding requirements for small cell wireless facilities if both of the following requirements are met:
(a) The authority imposes similar requirements in connection with permits issued for similarly situated users of the ROW.
(b) The purpose of the bonds is 1 or more of the following:
( i ) To provide for the removal of abandoned or improperly maintained small cell wireless facilities, including those that an authority determines should be removed to protect public health, safety, or welfare.
( ii ) To repair the ROW as provided under section 13(10).
( iii ) To recoup rates or fees that have not been paid by a wireless provider in more than 12 months, if the wireless provider has received 60-day advance notice from the authority of the noncompliance.
(2) An authority shall not require either of the following under subsection (1):
(a) A cash bond, unless any of the following apply:
( i ) The wireless provider has failed to obtain or maintain a bond required under this section.
( ii ) The surety has defaulted or failed to perform on a bond given to the authority on behalf of the wireless provider.
(b) A bond in an amount exceeding $1,000.00 per small cell wireless facility.
Collected 2026-09-14T18:32:31Z. Source file · JSON