GroundRules
← Search the law
Nebraska · Snapshot open-us-law v2026.08, retrieved 2026-09-14

Neb. Rev. Stat. § 61-508: Neb. Rev. Stat. § 61-508

Read at publisher ↗
Where this section sits in the code
  1. NE Code
  2. Chapter 61

(1) The department shall prepare a request for qualifications for design-build and progressive design-build proposals and shall prequalify design-builders and progressive design-builders. The request for qualifications shall describe the project in sufficient detail to permit a design-builder or a progressive design-builder to respond. The request for qualifications shall identify the maximum number of design-builders or progressive design-builders the department will place on a short list as qualified and eligible to receive a request for proposals.

(2) A person or organization hired by the department under section 61-505 shall be ineligible to compete for a design-build contract on the same project for which the person or organization was hired.

(3) The request for qualifications shall be (a) published in a newspaper of statewide circulation at least thirty days prior to the deadline for receiving the request for qualifications and (b) sent by first-class mail to any design-builder or progressive design-builder upon request.

(4) The department shall create a short list of qualified and eligible design-builders or progressive design-builders in accordance with the guidelines adopted pursuant to section 61-506 . The department shall select at least two prospective design-builders or progressive design-builders, except that if only one design-builder or progressive design-builder has responded to the request for qualifications, the department may, in its discretion, proceed or cancel the procurement. The request for proposals shall be sent only to the design-builders or progressive design-builders placed on the short list.

Collected 2026-09-14T18:32:21Z. Source file · JSON

Browse this collection