Neb. Rev. Stat. § 61-516: Neb. Rev. Stat. § 61-516
Where this section sits in the code
- NE Code
- Chapter 61
A design-build contract, a progressive design-build contract, and a construction manager-general contractor contract may be conditioned upon later refinements in scope and price and may permit the department in agreement with the design-builder, progressive design-builder, or construction manager to make changes in the project without invalidating the contract.