NRS 278.0195: “Utility project” defined.

Read at publisher ↗
Where this section sits in the code
  1. TITLE 22 — COOPERATIVE AGREEMENTS BY PUBLIC AGENCIES; REGIONAL TRANSPORTATION COMMISSIONS; PLANNING AND ZONING; DEVELOPMENT AND REDEVELOPMENT
  2. CHAPTER 278 - PLANNING AND ZONING
  3. GENERAL PROVISIONS

“Utility project” means:

1. An electric transmission line which is designed to operate at 200 kilovolts or more; or

2. A line used to transport natural gas which operates at 20 percent or more of the specified minimum yield strength of the material from which the line is constructed,

Ê which has been approved for construction after October 1, 1991, by the State or Federal Government or a governing body.