NRS 624.890: Contractor who commits certain violations may be required to obtain services of construction control.

Read at publisher ↗
Where this section sits in the code
  1. TITLE 54 — PROFESSIONS, OCCUPATIONS AND BUSINESSES
  2. CHAPTER 624 - CONTRACTORS
  3. RESIDENTIAL PHOTOVOLTAIC SYSTEMS USED TO PRODUCE ELECTRICITY

1. If a contractor who performs work concerning a residential photovoltaic system used to produce electricity is determined by the Board to have violated:

(a) One or more of the provisions of NRS 624.301 to 624.305, inclusive, 624.860, 624.870 or 624.875; or

(b) Any regulation adopted by the Board with respect to contracts for work concerning a residential photovoltaic system used to produce electricity,

Ê the Board may require that the contractor obtain the services of a construction control for each contract that the contractor enters into for work concerning a residential photovoltaic system used to produce electricity.

2. The contractor may not:

(a) Be related to the construction control or to an employee or agent of the construction control; or

(b) Hold, directly or indirectly, a financial interest in the business of the construction control.

3. As used in this section, “construction control” has the meaning ascribed to it in NRS 627.050.