GroundRules
← Search the law
Nevada · Through 2025 session (NRS as revised 2026-08-25)

NRS 704.7745: Final inspection by utility; temporary disconnection and reconnection of electric service relating to installation.

Read at publisher ↗
Where this section sits in the code
  1. TITLE 58 — ENERGY; PUBLIC UTILITIES AND SIMILAR ENTITIES
  2. CHAPTER 704 - REGULATION OF PUBLIC UTILITIES GENERALLY
  3. ELECTRIC SERVICE
  4. Net Metering Systems

1. If a customer-generator has received all the necessary inspections from any governmental entity required for the installation of a net metering system and submits to a utility a request for the completion of a final inspection by the utility, the utility shall complete the final inspection within a reasonable time after receipt of the request in accordance with the regulations adopted pursuant to NRS 704.773.

2. If a customer-generator submits to a utility a request to temporarily disconnect and subsequently reconnect electric service in relation to the installation of a net metering system, the utility shall schedule the temporary disconnection and subsequent reconnection within a reasonable time after receiving the request in accordance with the regulations adopted pursuant to NRS 704.773.

Collected 2026-09-03T05:51:47Z. Source file · JSON

Browse this collection