N.Y.C. Admin. Code § 28-118.4.3: § 28-118.4.3 Timeframe for application.

Read at publisher ↗
Where this section sits in the code
  1. New York City Administrative Code
  2. Title 28
  3. Chapter 1: Administration

The application for the certificate of occupancy must be submitted within six months of the final construction inspection. The department may refuse to issue a certificate of occupancy where the final inspection was completed more than six months prior to such application.

(L.L. 2021/126, 11/7/2021, eff. 11/7/2022)